Menekse Res

Menekşe Renewable Energy and Electricity Generation Inc.

Licensed Menekşe Wind Power Plant is located within Menekşe Renewable Energy and Electricity Generation Co. Menekşe WPP, established in Yozgat, Sorgun-Çekerek region, started to generate electricity in January 2025. It is planned to generate 73,500 MWh per year with a production capacity of 24 MWm on 177 acres of land. The targeted annual carbon emission amount of Menekşe WPP is 45,360 tonnes.

Teknik Veriler

LOCATION

LOCATION

Yozgat – Sorgun - Çekerek ve Araplı Köyleri

LICENSE DURATION

LICENSE DURATION

Mayıs 2023’den itibaren 49 yıl

LAND SIZE

LAND SIZE

177 dönüm

PRODUCTION AMOUNT - MWh / YEAR

PRODUCTION AMOUNT - MWh / YEAR

70,000,000 kWh/year

MWe (AC) / MWm (DC) POWER

MWe (AC) / MWm (DC) POWER

20 MWe / 24 MWm

ENERGIZED HOUSING

ENERGIZED HOUSING

30,000 pieces

Numeric Data

CONSULTANCY

CONSULTANCY

Renewatt

TURBINE BRAND AND TYPE

TURBINE BRAND AND TYPE

Goldwind GW 165

TOWER SIZE

TOWER SIZE

100 m

WING DIAMETER

WING DIAMETER

165 m

CARBON EMISSIONS

CARBON EMISSIONS

45,360 tons/year